Project Timeline

2000
2001
2002
2003
2004
2005
2006
2007
2008
2009
2010
Phase 1
Phase 2
Phase 3
  • Define Scope and Cost
  • Condition Assessment Study
  • Contract Framework with Atomic Energy of Canada Limited
  • Regulatory Processes
    • Public Utilities Board
    • Canadian Nuclear Safety Commission
    • Department of Environment and Local Government
  • Dr. Robin Jeffery Review
  • Preliminary Engineering for Risk Reduction
  • Province of New Brunswick Approval
  • Detailed Engineering and Procurement
  • Site Preparation
    • Construction of Waste Management Facilities and Temporary Facilities
  • Completion of Detailed Engineering
  • Material Procurement and Delivery
Define Scope and Cost
Early Start Activities
Project Approval
Pre-Outage Construction
Start of Planned Maintenence Outage